Judge refuses to halt work on St. Croix bridge

Published On: May 06 2013 04:41:37 PM CDT
STILLWATER, Minn. -

A federal judge has refused to halt work on the St. Croix bridge project to connect Minnesota and Wisconsin.

U.S. District Judge Richard Kyle refused Monday to grant an order sought by C.S. McCrossan Construction Inc. McCrossan is still pursuing a similar request before the Minnesota Court of Appeals.

The Star Tribune reports Kyle put McCrossan's federal lawsuit on hold until the state court rules.

Maple Grove-based McCrossan filed dual lawsuits against the Minnesota Department of Transportation. The lawsuit stems from MnDOT's awarding of a $58.1 million bid for the contract to complete approach work on the bridge, while rejecting McCrossan's low bid of $52.3 million.

MnDOT maintains McCrossan did not follow bid process instructions.

The project includes building a new four-lane highway across the St. Croix River.

Advertisement
  • Emma

    Emma

    Look Who's 3

    Check out who's turning 3, and send in your photo.

  • Call for Action logo

    Submit a Complaint to Call For Action

    Have a consumer complaint? Click here to contact our Call For Action team.

  • C3K-EVENTS

    Events calendar

    Looking for something to do? Visit Channel 3000's events section featuring dining, food, music and family-friendly events throughout Madison and the surrounding area.

Advertisement